TRANSPORTATION, IDAHO DEPARTMENT OF

Total received in grants · trailing 12 months
$69M
vs. GOVERNOR'S AUTHORIZED REPRESENTATIVE ($39.0B), largest tracked grant recipient
$1for every U.S. household÷ 131M U.S. households
In perspective
0.0%of all $162.9B in tracked grants
15separate grants, trailing 12 months

TRANSPORTATION, IDAHO DEPARTMENT OF has received $69M across 15 federal grants of $1M or more on record.

Data as of July 24, 2026. Source: USAspending.gov, prime contract awards $1M+. Federal spending data lags and has known gaps. This is not a real-time or complete record.

Grants by agency

Where this recipient’s grant dollars come from.

All grant awards

Swipe to see description and amount →

AgencyDescriptionAmount
PROJECT TITLE: US 93, CAREY TO HOTSPRINGS, BLAINE CO :::: PROJECT DESCRIPTION: THIS PROJECT IS TO REHABILITATE THE ROADWAY STARTING AT MILEPOST 203.000 TO MILEPOST 208.000 ON US-93 TO PROVIDE A NEW PAVEMENT SURFACE.
$9,527,737
PROJECT TITLE: US 30, SODA SPRINGS WCL TO ECL :::: PROJECT DESCRIPTION: THIS PROJECT IS FOR RECONSTRUCTION IN THE SODA SPRINGS CITY LIMITS, MILEPOSTS 404.366 - 406.786.
$9,367,000
PROJECT TITLE: I 15, EXIT 119 TO ROBERTS, BONNEVILLE/JEFFERSON COS :::: PROJECT DESCRIPTION: THIS PROJECT WILL APPLY A FULL WIDTH OVERLAY (0.15) FOLLOWED BY A FOG COAT. AFTER THE FOG COAT HAS BEEN APPLIED NEW PAVEMENT MARKINGS WILL BE APPLIED ALSO.
$8,656,389
PROJECT TITLE: I 15, BINGHAM CO LN TO MP 119, BONNEVILLE CO :::: PROJECT DESCRIPTION: PROJECT WILL CONSIST OF FULL WIDTH MILLING AND A 0.15' OVERLAY (1.8') THIS WILL ADD A NEW LAYER OF ASPHALT AND CREATE A NEW WEARING SURFACE AND ADD STABILITY TO THE EXISTING ROADWAY.
$5,365,498
PROJECT TITLE: I 90, PENNSYLVANIA AVE OPASS EB, CDA :::: PROJECT DESCRIPTION: THIS PROJECT WILL REPLACE THE EASTBOUND I-90 BRIDGE OVER PENNSYLVANIA AVENUE IN COEUR D'ALENE.
$5,169,478
PROJECT TITLE: SH 46, CITY OF GOODING :::: PROJECT DESCRIPTION: THIS PROJECT IS ANTICIPATED TO BE A 0.4' MILL AND INLAY THROUGH THE CITY OF GOODING.
$4,775,414
PROJECT TITLE: STC-1705, BANNOCK ST, MALAD CITY :::: PROJECT DESCRIPTION: THIS PROJECT WILL RECONSTRUCT APPROXIMATELY 0.7 MILES OF BANNOCK STREET, WHICH RUNS THROUGH THE CENTER OF MALAD CITY. ROUTINE MAINTENANCE HAS KEPT THE ROADWAY DRIVABLE, BUT THE HEAVY TRUCK TRAFFIC ALONG THE ROUTE HAS DETERIORATED THE PAVEMENT SECTION. A MAJOR WATER SYSTEM UPGRADE IN THE RECENT PAST HAS LEFT THIS ROUTE WITH MANY UTILITIES PATCHES. THE ROADWAY NEEDS A COMPLETE RECONSTRUCTION TO RE-ESTABLISH A PROPER PAVEMENT SECTION.
$4,746,600
PROJECT TITLE: I 15, ROBERTS TO SAGE JCT, JEFFERSON CO :::: PROJECT DESCRIPTION: THIS PROJECT WILL MILL IN GUARDRAIL AREAS IN ORDER TO KEEP EXISTING GUARDRAIL AT STANDARD HEIGHT AND ALSO UNDER EXISTING STRUCTURES TO MAINTAIN THE EXISTING CLEARANCE OF THE ROADWAY AND STRUCTURES. THIS WILL BE FOLLOWED BY A FULL WIDTH OVERLAY OF 0.15 DEPTH.
$4,373,495
PROJECT TITLE: STC-2713, 3700 NORTH RD, TWIN FALLS CO :::: PROJECT DESCRIPTION: OVERLAY, RECONSTRUCTION AND SHOULDER WIDENING
$4,310,593
PROJECT TITLE: I 84, B, FY25 SH 81 TO I 84, BURLEY :::: PROJECT DESCRIPTION: THE I 84B BURLEY, SH 81 TO I 84 PROJECT IS LOCATED IN THE CITY OF BURLEY IN CASSIA COUNTY. IT WILL REPAIR THE CRACKING THAT HAS OCCURRED ON I 84B BURLEY (AKA MAIN ST OR US30) BETWEEN SH81 AND I84 IN ORDER TO PRESERVE THE LIFE OF THE EXISTING ROADWAY.
$3,667,816
PROJECT TITLE: US 95, LITTLE SALMON RIVER BRIDGE :::: PROJECT DESCRIPTION: THIS PROJECT WILL REPLACE THE LITTLE SALMON RIVER BRIDGE ON HWY-95 AT MILEPOST THIS IS A DUP WITH KEY # 13388.
$3,104,988
PROJECT TITLE: I 90, PENNSYLVANIA AVE OPASS EB, CDA :::: PROJECT DESCRIPTION: THIS PROJECT WILL REPLACE THE EASTBOUND I-90 BRIDGE OVER PENNSYLVANIA AVENUE IN COEUR D'ALENE.
$1,920,412
PROJECT TITLE: STATE, FY26 D3 BRIDGE REPAIR :::: PROJECT DESCRIPTION: THE FY26 BRIDGE REPAIRS PROJECT IS LOCATED IN DISTRICT 3 AND WILL PROVIDE BRIDGE DECK PRESERVATION AND PREVENTATIVE MAINTENANCE TO VARIOUS BRIDGES IN THE DISTRICT.
$1,391,365
SH 51, SOUTH SIDE CANAL CULVERT, OWYHEE CO
$1,129,317
PROJECT TITLE: STC-2713, 3700 NORTH RD, TWIN FALLS CO :::: PROJECT DESCRIPTION: OVERLAY, RECONSTRUCTION AND SHOULDER WIDENING
$1,104,225